Fire Tower Road

The Fire Tower Road project was a remediation development of an old landfill for Chattahoochee County in 2016. remediation of old landfill, removal of concrete debris, regrading of slope to prevent contamination and erosion, installed storm sewer system and methane observation system

Acting as the primary contractor, ACCI executed the sitework scope which included but was not limited to the following:

  • 600 cubic yards of concrete debris removed
  • Imported 20,000 cubic yards of local dirt in order to fill the site and grade the slope to prevent erosion and soil contamination
  • Installed storm sewer system and a methane observation system

Click any image below to view gallery.