The Spencer High School project started development in 2016 as a joint venture between Freeman & Associates and Ra-Lin & Associates in Columbus, Georgia.

ACCI executed the complete sitework scope package which includes but is not limited to the following:

• Site clearing of 26 acres
• 18,000 Yards of dirt on site to be moved along with over 230,000 cubic yards of dirt hauled in
• Underground Utility Systems with over 13,500 LF of pipe
• Placed over 11,000 tons of graded aggregate base on site