Columbus Justice Center, started in 2024 is an ongoing municipal project for Columbus Consolidated Government, designed by TLC Engineering Solutions. The architects for this project include The SLAM Collaborative & Barnes Gibson Partners Architects. Gilbane is the general contractor on this project who has contracted with Freeman & Associates for a portion of the project.
ACCI is in the process of completing the sitework scope package which includes but is not limited to the following:
- 26,315 cubic yards of dirt moved
- Underground Utility Systems
- Removing curb & gutter, sidewalk, and other structures
- Asphalt
- Curb & Gutter
- Temporary pond, grassing, and erosion maintenance